What the Review Clock Actually Covers
Florida law sets the pace of plan review for most residential permits. For a single-family unit under 7,500 square feet reviewed by a local government plans reviewer, the local government must act within 30 business days after it receives a complete and sufficient application. Larger homes get a longer window. The timeframe can be waived in writing, and many jurisdictions offer a standard waiver form because it allows reviewers and applicants to run comments back and forth without restarting the count.
Before the count starts, the jurisdiction checks the application for completeness. Under the same statute, it must tell you in writing within 5 business days which information is missing. If it does not, the application is deemed complete. The statute does not limit how many times a local government may ask for additional information, which is why a thin first submission can cost more than one round.
A missed deadline does not approve the permit. The statute does not provide deemed approval for it. It requires the local government to reduce the building permit fee for each business day it misses the deadline, with exceptions for written extensions, delays caused by the applicant, and extraordinary circumstances. The practical effect is that the jurisdiction's clock is real, but it only protects you when the application was complete and every comment is answered on time.
| Stage | What happens | Who controls the pace |
|---|---|---|
| Completeness check | The jurisdiction confirms the application and drawings are all there. Orlando states 5 business days. | The jurisdiction, once the set is submitted |
| Review | A plans reviewer checks the set against the code. State law sets 30 business days for a single-family home under 7,500 square feet. | The jurisdiction |
| Corrections | Comments come back and the set is revised. Orlando requires corrections within 10 business days or the application is denied and must be resubmitted. | The applicant and the design team |
| Resubmittal | The corrected set goes back in for another check. | Shared: your speed in, theirs out |
What Reviewers Compare Against What
A reviewer rarely finds a mistake in a single sheet. The comments come from comparing sheets with each other. The window tagged on the front elevation is checked against the window schedule and against its product approval. The finished floor elevation on the site plan is checked against the floor level on the elevations. The roof pitch on the roof plan is checked against the pitch drawn on every elevation. Orange County asks for one set of electronically signed and sealed construction documents, then sends it to every reviewing agency at the same time, and it will not issue a building permit until all required reviews are complete.
That is why a drawing that looks complete can still be returned. Each sheet was right on its own. Two of them disagreed.

Four Places Where Sets Stop Agreeing
- Openings: a window or door that appears on a plan or elevation but not on the schedule, or in a different size
- Levels: finished floor, ceiling, and roof heights that differ between the site plan, the floor plans, and the elevations
- Roof: a pitch or material on one sheet that does not match the roof plan, the energy calculation, or the product approval
- Site: a building footprint that is closer to a property line than the setback allows, or a grading plan that does not move water away from the house

Why the Seal Is a Question About the Set, Not the Stamp
Orange County asks for signed and sealed documents. Not every sheet in a permit set requires a seal: that depends on the discipline the sheet belongs to and on what the jurisdiction accepts. What matters at submission is that the sealed sheets and the unsealed ones describe the same building. Engineering that was done late and drawn from an earlier version of the plan is one of the more common reasons two sheets disagree.
How a Permit-Ready Set Is Built
- The existing conditions and the parcel are documented first: survey, setbacks, grade, utilities.
- The floor plan is approved before the elevations are developed on top of it, so levels are set once.
- Engineering and the site plan run in parallel with the drawing set and are reconciled to it before issue.
- Schedules, product approvals, and calculations are compiled from the final drawings, not from earlier ones.
- Every sheet is checked against the sheets it relates to before the set is submitted.
That sequence is what a permit-ready plan set means in practice: not a prettier drawing, but one where the reviewer has nothing left to reconcile. If you would rather hand the submission and the comment cycle to someone else, Permit Runner carries the set through plan review until the permit is issued.
Plan Review Is Not the Final Inspection
Owners often use the two words as if they were one. Plan review happens before construction starts: the city or county checks your drawings against the code, and the permit is issued once the set clears. Final inspection happens after construction, when the building official visits the site to confirm that the completed work matches what was approved. One reviews the documents, the other reviews the building. A set that clears the first has to be built exactly as drawn to clear the second, which is another reason the drawings and the schedules must agree before anyone starts framing.
What to Do the Day Comments Arrive
A comment letter is not a refusal. It is a list. Read it for the comments that point to a disagreement between sheets, because those are the ones whose fix changes more than one drawing. Answer all of them in one resubmittal rather than in installments, and track the deadline your jurisdiction sets: in Orlando, corrections not submitted within 10 business days mean the application is denied and has to be resubmitted with the plans and fees. Our own turnaround on any city or county comment is one to two business days, which is on the FAQ page along with the rest of how the process works.
The review timeframes in this article come from Florida Statute 553.792 (2025) and from the City of Orlando's published permit guidelines, linked in the sources below, and were accurate when this was written. Correction deadlines, waiver forms, and submittal portals differ by jurisdiction and change over time. Confirm the current rules with your building department, or send us the address and we will confirm them for you.